4.5.2.3 Splashproof and spraytight. Test the control-panel assembly case in accordance with
MIL-STD-108. Close and clamp the cover prior to start of test. Indication of moisture inside the control-
panel assembly case shall constitute failure of this test.
4.5.2.4 Operational reliability. Operate the control-panel assembly from a 115 volt, AC, 60 Hz power
source. Test the control-panel assembly with a 100 watt load on each of the four circuits for 50 hours at
maximum voltage. Turn the circuit breaker switch off and on manually after each 1 hour period.
Malfunction of any component shall constitute failure of this test.
5. PACKAGING
5.1 Packaging. For acquisition purposes, the packaging requirements shall be as specified in the
contract or order (see 6.2). When packaging of material is to be performed by DoD or in-house contractor
personnel, these personnel need to contact the responsible packaging activity to ascertain packaging
requirements. Packaging requirements are maintained by the Inventory Control Point's packaging
activities within the Military Service or Defense Agency, or within the Military service's system commands.
Packaging data retrieval is available from the managing Military Department's or Defense Agency's
automated packaging files, CD-ROM products, or by contacting the responsible packaging activity.
5.2 Marking. Packages and shipping containers shall be marked in accordance with MIL-STD-129.
6. NOTES
(This section contains information of a general or explanatory nature that may be helpful, but is not
mandatory.)
6.1 Intended use. The control-panel assembly is intended to be used to regulate and adjust the
voltage to the various circuits in portable heliport lighting installations.
6.2. Acquisition requirements. Acquisition documents should specify the following:
a. Title, number, date of the specification, and the complete military or contractor's type or part
number, as applicable (including the CAGE).
b. When first article inspection is required and the time frame required for submission of the first
article control-panel assembly (see 3.2).
c. Color required (see 3.9).
d. ASSIST Online database should be cited in the solicitation, and if required, the specific issue of
individual documents referenced. If not otherwise specified, the versions of the individual
documents referenced will be those in effect on the date of release of the solicitation (see 2.1).
c. Packaging requirements (see 5.1).
6.3 First article. Any changes or deviations of production control-panel assemblies from the approved
preproduction model during production will be subject to the approval of the contracting officer. Approval
of the first article model will not relieve the contactor of his obligation to furnish control-panel assemblies
conforming to this specification.
6.4 Data requirements. The contracting officer should include requirements for such data as technical
publications, instructional materials, illustrated parts lists, and contactor's maintenance and operation
manual to be furnished with each control-panel assembly.
6.5 Provisioning. The contracting officer should include provisioning requirements for repair parts and
maintenance tools as necessary (including any special tools), and instructions on shipment of control-
panel assemblies.